Project Description

Project Details:

CMID provided project manager and design engineer services: responsible for preliminary and final design, construction administration services to help plant reach goal of 100-mgd. Work included enhancing control of existing systems via SCADA, replacing and retrofitting existing MCCs and other electrical equipment to help increase flow throughout facility. Site lighting, as well as interior building lighting, was replaced as necessary.

The RAS pumping system on the secondary clarifiers was redesigned, involving construction of a submerged pumping station with four large motors powered by VFDs.