Project Description

Project Details:

CMID worked with Applied Engineering and Affiliated Engineers to provide Commissioning of the Fifth Third Bank Office Building, as part of the Campus Commissioning Process. The office building was designed to attain LEED Silver accreditation. It provides office space, public use space and clinical services to support the Wishard Hospital Campus, a cafeteria and coffee shop, and a connection between the parking garage and Ambulatory Care Building. The building is approximately 300,000 sf.

CMID acted as the Commissioning Authority for the building, providing documentation for the Contractors to use during installation of equipment (Installation Verification Checklists) and testing of the building systems as a whole (Functional Performance Testing), as well as onsite construction phase reviews, to ensure the system was built as designed.